Control Room/Risk & Dependencies
Mission Active

Risk & Dependencies

Integration hotspots, dependency chains, and key blockers across current and proposed architecture. Scored by impact and likelihood to inform sequencing constraints.

DraftUpdated 17 Mar 2026Deprecation PlanDecisions

Why this matters

Unmitigated risks will delay or derail the transformation. This register quantifies exposure and maps dependencies that constrain sequencing.

What this informs

Deprecation sequencing, Phase 1 scope constraints, and the steering committee risk appetite conversation.

What remains unresolved

Dependency chain mapping incomplete. Dealer adoption risk requires field validation. Cost accuracy risk blocked by scenario selection.

Total Risks

8

Critical

2

High

5

Domains Affected

6

Mitigations Defined

6

CriticalHighMediumLowMinimal
002
001
005
007
006
004
008
RareUnlikelyPossibleLikelyAlmost certain
RSK-00120
In progress

Legacy integration brittleness during migration

Impact
Likelihood

Façade layer isolates new components. Incremental migration with rollback capability at each stage. Integration test suite before each cutover.

IntegrationArchitecture Lead
RSK-00215
Decision needed

Data sovereignty non-compliance in China operations

Impact
Likelihood

Parallel China architecture track. Independent data storage. Legal review of all cross-border data flows. ICP licensing ahead of deployment.

RegulatoryRegional Architect
RSK-00312
Under review

Vendor lock-in through monolithic platform selection

Impact
Likelihood

Composable architecture preference. API-first contracts. Avoid proprietary data formats. Exit cost analysis in vendor evaluation.

StrategyEnterprise Architect
RSK-00412
In progress

Organisational resistance to domain-driven boundaries

Impact
Likelihood

Stakeholder alignment workshops. Domain ownership mapped to existing reporting lines where possible. Executive sponsorship for boundary changes.

OrganisationalProgram Manager
RSK-00512
Draft

SAP upgrade cycle misalignment with migration timeline

Impact
Likelihood

Early alignment with SAP team on upgrade roadmap. Integration layer absorbs API version changes. Feature-flag migration phases around SAP releases.

IntegrationSolution Architect
RSK-0069
In progress

Insufficient observability in transitional architecture

Impact
Likelihood

Observability as day-one requirement. OpenTelemetry standard. Monitoring dashboard for all integration touchpoints. Alert thresholds defined before go-live.

OperationsArchitecture Lead
RSK-00716
Draft

Dealer network adoption lag for new service interfaces

Impact
Likelihood

Progressive rollout by region. Dealer feedback loop built into Phase 1. Training programme. Dual-interface period during transition.

OrganisationalProgram Manager
RSK-00815
Blocked

Cost estimation accuracy for future-state scenarios

Impact
Likelihood

Order-of-magnitude ranges, not point estimates. Scenario-based costing. Vendor pricing validated against reference implementations. Contingency buffer defined.

GovernanceProgram Manager

Integration Dependency Chain

Critical path dependencies between systems. Highlights single points of failure and cascade risks during migration.

Draft

Architecture Lead

Data Flow Reliability Map

Data freshness and reliability across integration touchpoints. Flags where eventual consistency may affect business operations.

Draft

Solution Architect

blocking

Cost estimation depends on scenario selection

Blocks: DEL-009 — High-Level Platform Cost Estimate

blocking

China data sovereignty assessment not initiated

Blocks: DEL-007 — China Architecture Annex

at-risk

SAP upgrade roadmap not confirmed

Blocks: ADR-006 — SAP retention decision

Decision Layer

Decisions Supported

ADR-001 (strangler-fig), ADR-004 (China track). Risk profile shapes sequencing and scope constraints.

Dependencies

Risk profile informs deprecation sequencing and Phase 1 scope definition. Blocks DEL-005 completion.

Next Actions

Complete dependency chain mapping. Define risk appetite thresholds with steering committee.

Confidence

Low-Medium — heatmap populated but dependency chain and dealer adoption risk require further validation.